A New Stoplight and Two Roundabouts Are Coming to the Crested Butte South Commute

A quiet walking path curves past a late-autumn meadow toward timber-sided homes beneath snow-dusted hills in a Colorado mountain valley.

The drive from Crested Butte South to town starts where Cement Creek Road meets Highway 135. For years it has been one of the simplest parts of living in the south end of the valley. You turn onto the highway, pass Riverland and Brush Creek Road, and come into town on Sixth Street at the Four-Way stop.

Over the coming year, almost every intersection on that drive is scheduled for work. A temporary stoplight goes up at the Whetstone housing site in January. Brush Creek Road gets a roundabout and a pedestrian underpass, and the Red Lady Avenue intersection in town gets a roundabout of its own. Both roundabouts are set for the same construction year. Back in CB South, the bus system is adding a second pullout. Anyone weighing CB South against town over the next twelve months will be test-driving a corridor that is partway through a rebuild. The finished corridor runs slower, has more places to cross on foot, and is built around the free bus.

Brush Creek Road gets a stoplight in January

The biggest change sits at Highway 135 and Brush Creek Road, the site of Gunnison County's Whetstone community housing project. The Crested Butte News described it as a 252-unit development in October 2026. The long-term plan is a roundabout at the Brush Creek intersection plus an underpass so pedestrians can get under the highway to the RTA bus stop.

The underpass will not be ready by the time the first tenants move in. The county's September 14, 2026 letter to the town said federal and CDOT design and permitting review kept construction from starting in 2026. It set a spring 2027 start and an underpass finished "by fall" of 2027. To cover the gap, the town and county agreed at the October 19 council meeting on a temporary fix. As the Crested Butte News reported, it is a pedestrian-activated HAWK signal that brings highway traffic to a full stop. It comes with a 40 mph speed limit, narrower lanes, warning signs, rumble strips and a painted crosswalk between the bus stop and the area just north of the Whetstone entrance. The setup was expected to start in January and stay until the permanent work is done next summer. The county expected to begin leasing units in January.

For a CB South commuter, that means a 40 mph zone and a signal that can stop traffic at any hour. That stretch has been posted at 45 mph for close to 18 months because of construction, so the slowdown starts from a lower base than most drivers remember. The same report said the sheriff will work with Mt. Crested Butte to enforce the 40 mph limit.

There is also a turning detail to know. Mayor Ian Billick said the Whetstone entrance and Brush Creek Road do not line up directly, which could cause confusion with left turns at both. In September, county staff told the town council that left turns out of the project are hard during peak highway hours. Their suggestion was to turn right, loop through the Riverland roads and use the acceleration lanes to head north, which they called a common professional driving strategy. CB South drivers heading north will be sharing that stretch with this new turning traffic.

The roundabout follows in the spring

The stoplight is a stopgap. In October, county staff told commissioners they were interviewing contractors for the permanent Brush Creek roundabout, planned to go out to bid early in 2027, and expected to start "as soon as weather allows in the spring." The county also said that once construction starts, the work zone will have a reduced speed limit, flaggers and bypass traffic lanes.

The project is paid for in part by a $15 million federal Safe Streets for All grant awarded to Gunnison County. In 2025 the underpass alone was estimated at $2.3 million. The county's plan for that site does not include a park-and-ride. It labels land there as future trailhead parking to be "constructed by others."

Red Lady Avenue lands in the same year

At the other end of the drive, the Town of Crested Butte and the Gunnison Watershed School District plan a roundabout at Highway 135 and Red Lady Avenue. It is meant to handle traffic from the Crested Butte Community School expansion. The town's February 2026 release describes a "peanut-shaped" design meant to work for both Red Lady Avenue intersections. It is supposed to slow traffic, shorten pedestrian crossings and reduce conflict points, especially at school drop-off and pickup. The release lists $2.2 million in Safe Streets for All funding for the project.

That release had construction starting in the fourth quarter of 2026. The town's third-quarter financial update in its November 16, 2026 council packet says the Red Lady roundabout "now moves to 2027." The town's project page lists a spring 2027 groundbreaking.

Taken together, the north end of the valley is set to have two roundabout projects on Highway 135 in one building season. When the Crested Butte News first reported the plans in October 2025, both were scheduled for 2026. Both have now moved into 2027, and the CB South commute crosses each of them.

The intersection at Cement Creek Road has no date

The intersection closest to home for CB South residents is the one with the least planning so far. The same October 2025 report said a third roundabout, at Highway 135 and Cement Creek Road, is meant to fix another problem intersection in the North Valley, with plans to come "at a later time." If you are looking at a home near the CB South entrance, today's intersection is the one you will be using for the foreseeable future.

The bus comes further into CB South

The free Gunnison Valley RTA bus runs from Gunnison up Highway 135 through Crested Butte to Mt. Crested Butte, with a stop at CB South. In early November the RTA board hired SCJ Alliance for a package of bus stop improvements. It includes a new pullout at the CB South POA office area to serve the subdivision's commercial area. The Crested Butte News put the cost of four stop improvements plus the new pullout at an estimated $260,000. That brings a stop closer to the commercial core we wrote about in how CB South grew around two streets.

The same RTA report gives the current numbers. Ridership was down 8.4% for 2026 through the summer report, and 2.2% of scheduled trips were missed in August, mostly because of driver shortages. Ten buses were in service and five out of service. The winter schedule runs 41 round trips. The board plans to raise that to 46 in 2028, with 15-minute service from 6:30 to 9:30 a.m. and 3 to 5:15 p.m. and 30-minute service the rest of the day. It scaled that back from an earlier 53-trip goal because RTA sales tax revenue is projected to be about 3% lower in 2026 than in 2025.

In town, the Mountain Express town bus starts its winter season on November 25. It is scheduled to run every 15 minutes from 7:10 a.m. to midnight through April 4, 2027, with stops at the Four-Way and the Mt. Crested Butte Transit Center. For a CB South household, getting to the lifts by bus means an RTA ride north and a transfer at the Four-Way.

What this means for choosing CB South

Most buyers comparing CB South with town measure the drive in minutes. Over the next year the drive itself changes. Starting in January there is a 40 mph zone and a stoplight at Brush Creek, and by spring there are construction zones at Brush Creek and Red Lady in the same season. The roundabouts and the underpass are designed for lower speeds and for people on foot getting to the bus.

If you are touring CB South homes this winter, drive the corridor at the hours you would actually commute, and ride the RTA once if a bus commute is part of your plan. A short trip from a showing in CB South to a coffee on Elk Avenue in January will feel different from the same trip in July. The library project, covered in what the library lawsuit shows about CB South design review, is a reminder that the subdivision itself is still changing too. Our Crested Butte South neighborhood page covers the rest.

If you already own in CB South and are deciding whether to list in 2027 or wait, Crested Butte Homes can tell you how the corridor work fits your timing. To start that conversation with real numbers, request a free home valuation.